Why "Fixed-Price" Quotes Don't Exist in Italy (and How to Control the Budget)

Question about your property? Call: +39 329 973 6697

"Fixed price" in Italian renovation usually means fixed for what was described. Everything not described becomes an extra. Budget control starts with what you put on paper.

Start hereWhatsApp

A corpo and a misura

Why prices move

Tools that actually control cost

  1. Executive drawings and specifications before asking for quotes.
  2. A computo metrico priced by every contractor.
  3. A contract with agreed unit prices for variations.
  4. Progress payments only against measured works.
  5. A contingency of 10–15% kept by the owner, not included in the contract.
  6. Every variation approved in writing with updated cost.

For owners abroad

Our reports show the approved budget, variations and their impact on the total at every update, so there are no surprises at the end. Read how we report to remote clients.

Frequently asked questions

Can I get a truly fixed price for a renovation in Italy?

A lump-sum contract can be stable if drawings and specifications are complete; unknowns in old buildings still need a measured component or a contingency.

How much contingency should I keep?

At least 10–15% of the works budget, more for heavily degraded historic buildings.

How are variations priced?

Using the unit prices agreed in the contract and computo, approved in writing before the work is done.